Community Update

Building the next chapter of St Aloysius College

St Aloysius College is growing from a Year 11–12 senior college into a co‑educational Year 7–12 College. This page explains what’s being built, when, and what it means day-to-day for our school community. It will be updated as work progresses on site.

Block D construction underway

2 Cross Rd, Burraneer

Est. completion: end of 2028

Yr 7–12

Co-educational college

Block D

Current construction stage

End of 2028

Estimated completion

Why we’re building

Making room for a growing college

For decades, St Aloysius College was a Year 11-12 senior college only. In 2024 it welcomed its first Year 7 cohort as part of a transition to a comprehensive, co-educational Year 7–12 college. Demand has been strong — Year 7 places have already needed to be capped while the campus catches up with permanent facilities.

In the meantime, a significant part of teaching has been happening in demountable classrooms, and specialist spaces like science labs and food technology are stretched. This project replaces those temporary arrangements with permanent, purpose-built learning spaces, in a design shaped by the site’s setting between Cross Road and Gunnamatta Bay.

The project has been developed with the college Principal, the Parish, local council and neighbouring residents. It is being delivered under a Development Application approved by Sutherland Council. Which sets a condition of 780 students as the college’s approved enrolment capacity.

At a glance

Architect

Woods Bagot

Project manager

Currie & Brown

Delivery model

Design & Construct

Current stage

Block D construction

Also underway

Public Domain & Block A tender

The works

What’s being built

The approved works focus on two buildings: the existing library and the site’s main teaching building.

Block D

Existing library

Block A

New teaching building

Underway

New Administration & new teaching building

  • The current library (Block D) is refurbished into the college’s new Administration, Reception and Staff areas, with compulsory accessibility upgrades.
  • The current Administration building (Block A) will be demolished and replaced with a new three-level building containing general learning spaces, science laboratories and science learning spaces, a food technology kitchen, a staff hub and a new library.
  • Public domain works funded by Sydney Catholic Schools include two new pedestrian crossings (one on Cross Road and one on Burraneer Bay Road), widening of Cross Road to improve traffic circulation, and a new school street frontage including the rectification of non-compliant car parking.
  • The Chapel is relocated to the south of the field as part of these works.

Program

Project milestones

The works are being delivered as three coordinated programs — refurbishing the library into Administration (Block D), Council-required public domain and carpark upgrades, and the new teaching building (Block A) — each with its own procurement and construction schedule.

Block D — Administration & entrance

Apr 2026

Head Contractor awarded

Complete

3 Jun 2026

Contract executed

Complete

Jun 2026

Site establishment & construction underway

In progress

Q4 2026

Practical completion & handover (anticipated)

Upcoming

Public domain & carpark works

Ongoing

Council & Sydney Water design approvals

In progress

Q4 2026

Construction (roads, footpaths, water mains, carpark)

Upcoming

Q2 2027

Handover (anticipated)

Upcoming

Block A — New teaching building

May 2026

Head Contractor tender closed

Complete

Q3 2026

Head Contractor award (anticipated)

In progress

2027

Construction begins, following public domain works

Upcoming

End of 2028

Practical completion & handover (anticipated)

Upcoming

On site

Latest updates

Jun 2026

Construction begins on Block D

Following contract execution in early June, the head contractor has established their site compound and begun refurbishment of the Administration building (Block D). The Chapel is being relocated and a temporary library demountable established to allow this work to proceed.

May 2026

Public domain & Block A tenders under evaluation

Tenders for the Council-required public domain works (road, footpath and pedestrian crossing upgrades) and the new Block A teaching building closed in May 2026 and are being assessed, with a Head Contractor appointment expected in the coming months.

Next update

Check back here for the next construction milestone

This section is reviewed and updated regularly as works progress.

Community

Getting around during construction

Keeping students, staff, families and neighbours safe and informed is our priority throughout the build.

Site kept separate from school

The construction zone is hoarded and has its own contractor access point and compound, entirely separate from areas used by students and staff.

Traffic & parking improvements

Works include a widened Cross Road footpath, new pedestrian crossings on Cross Road and Burraneer Bay Road, additional bus bays, a water mains upgrade, and an extended car park.

Respecting our neighbours

The design has been shaped in consultation with residents on Cross Road, with building heights and placement chosen to protect existing views wherever possible.

Stay Informed

Questions about the building works?

This page will continue to be updated as the project progresses.For anything not answered here, get in touch.

Thank you for your interest. It has been sent.
There was an error trying to send your message. Please try again later.

COLLEGE OFFICE

St Aloysius College
2 Cross Rd, Burraneer NSW2230

BUILDING WORKS ENQUIRIES

Sydney Catholic Schools
Property & Facilities